1. Confirm contractual schedule requirements
Begin with the contract documents. Review required milestones, notice-to-proceed assumptions, completion dates, activity coding, calendars, submittal expectations and report format.
A baseline schedule establishes the project's time-management reference. Reviewing the logic and assumptions early can help owners, contractors and resident engineers avoid unclear progress reporting later.
Begin with the contract documents. Review required milestones, notice-to-proceed assumptions, completion dates, activity coding, calendars, submittal expectations and report format.
Trace the planned construction sequence from mobilization through closeout. Look for missing ties, illogical out-of-sequence work and assumptions that do not match site access or work restrictions.
Review whether activity durations and work calendars are plausible for the construction methods and conditions. Check hard constraints and unusual float values for explanation.
Evaluate the continuous driving path to completion and confirm that the schedule reflects relevant field dependencies, procurement and required agency coordination.
Record each observation with an activity reference, why it matters and the action requested. CPMForge describes automated QA/QC findings, narrative output and an Excel review comments workbook to support this work.
No. Contract provisions and the applicable agency's written requirements control the review.
No. Quality checks can help identify issues, but sequencing, constructability and contractual compliance require professional review.
The baseline schedule, narrative, relevant contract milestones, calendar details, procurement assumptions and a tracked comments/responses log.
CPMForge supports software-assisted review. Always compare the results against applicable contract documents and project requirements.